Strobbo can automatically calculate your scheduling based on imported resource needs.


Please note, this function is not free. If you would like to use our autoscheduling feature, please ask for more information via our chat.

This guide is broken down into the following subsections:

Where do I find autoscheduling?

You can find autoscheduling in both the daily and weekly planning screens.
To start automatic scheduling, first navigate to the daily or weekly overview.

Then, click in the sidebar on the autoscheduling symbol.

If you hover your mouse over the autoscheduling module symbol, “Calculate scheduling” appears.

How does autoscheduling work?

If you want to use autoscheduling based on resource needs, you first need to upload your resource needs.

After uploading your “Resource needs” you can start calculating scheduling.

Resource needs

The connection is usually created by the client’s IT team.

If your needs are not automatically supplied via our API, you can manually upload them as follows:

  • Go to the daily or weekly planner

  • Click the autoscheduling icon

  • Click “Upload resource needs”

  • Select the correct files

  • If necessary, tick “Overwrite existing files”. Otherwise, simply click “Upload”.

Ensure that everyone has an autoscheduling profile

During your training period with Strobbo, we will work with you to configure autoscheduling and create multiple autoscheduling profiles.

We can determine the rules of the scheduling for each profile to define what you consider to be optimum scheduling. For example, we define how many days and hours someone can work in a week.


You cannot set up these profiles yourself. The Strobbo technical team does this for you.

Important: ensure that there is a linked autoscheduling profile for everyone we need to calculate a schedule for.

When applying needs to users, the system takes into account the applicable rules from their profile.

How do I start autoscheduling?

  • First, go to the day or week planner.

  • Make sure you have uploaded your resource needs.


Note: you must upload resource needs for every day.
If you have not done this, you’ll see a notification.
Of course, if necessary, you can force-start scheduling without doing this by clicking “Yes” but no schedule will be created for the days that don’t have resource needs uploaded.

  • The system will then start calculating. The following message tells you it has started.

  • When the schedule has been fully calculated, you’ll return to the work schedule.

  • If necessary, you can now make any changes.

How do I stop autoscheduling?

If you want to cancel the autoscheduling, you can do this at any time by clicking on the red “Cancel calculation” button.

The system then asks if you are sure. If you definitely want to cancel, click “yes”.

How do I view the autoscheduling status?

Go to the daily or weekly planner and click on the autoscheduling symbol. You will then see an overview of who started (and cancelled, if relevant) the scheduling.